Jan 14, 2014 - 8. Upgrade Methodology and Phases. Deploy. Transition. Production Go-Live. End-user Training. Construct.

0 downloads 3 Views 235KB Size

Recommend Stories


Fuel System Overview The Fuel System (Overview)
Raise your words, not voice. It is rain that grows flowers, not thunder. Rumi

System Overview
Do not seek to follow in the footsteps of the wise. Seek what they sought. Matsuo Basho

Overview of Observing System Experiments
No amount of guilt can solve the past, and no amount of anxiety can change the future. Anonymous

Overview of Magnetron Sputtering System
The only limits you see are the ones you impose on yourself. Dr. Wayne Dyer

University Purchasing Overview
Don't watch the clock, do what it does. Keep Going. Sam Levenson

The Innovation Gap of Italy's Production System
What we think, what we become. Buddha

2017 gap cover product range overview
Everything in the universe is within you. Ask all from yourself. Rumi

V2 System Overview
Suffering is a gift. In it is hidden mercy. Rumi

Blue Waters System Overview
Never wish them pain. That's not who you are. If they caused you pain, they must have pain inside. Wish

Auger Mixing System Overview
No matter how you feel: Get Up, Dress Up, Show Up, and Never Give Up! Anonymous

Idea Transcript


PeopleSoft Financials Application Upgrade and Fit/Gap Session Overview David Nisbet January 14, 2014

© 2014 Board of Regents of the University System of Georgia. All Rights Reserved.

WebEx Housekeeping ALL AUDIO will be handled via conference call today. Please dial in: (646) 307-1300, access code 9759227

© 2014 Board of Regents of the University System of Georgia. All Rights Reserved.

2

WebEx Housekeeping • Submit questions via the chat function to all participants • We may hold some of the questions until the end of the presentation • Recording and slides will be available later today or tomorrow

© 2013 Board of Regents of the University System of Georgia. All Rights Reserved.

3

Agenda

• Application Upgrade Scope and Goals • Overview of Application Upgrade Phases and Timeline • Fit/Gap Process and Upcoming Sessions • Fit/Gap Schedule • Fit/Gap Participant Roles and Responsibilities • Q&A

© 2013 Board of Regents of the University System of Georgia. All Rights Reserved.

4

Application Upgrade Scope • Upgrade to Version 9.2/PeopleTools 8.53 • Integrate with current partners • Comply with Federal, State, and USG-required reporting • Training and documentation • System performance management and monitoring

© 2013 Board of Regents of the University System of Georgia. All Rights Reserved.

5

Application Upgrade Scope Not in scope: • Introduction of new modifications • Introduction of new modules

© 2013 Board of Regents of the University System of Georgia. All Rights Reserved.

6

Application Upgrade Goals • • • • • • • •

Reduce modifications Reduce complexity Increasing standardization, i.e., chart of accounts Improve expense functionality Improve Budget Preparation functionality Better align support resources Develop a mobile strategy Increase automation of current manual processes

© 2013 Board of Regents of the University System of Georgia. All Rights Reserved.

7

Structure

Plan

Upgrade Methodology and Phases Project Charter Customization Analysis Fit/Gap Analysis

Construct

Project Plan Upgrade Initial Pass Convert Reports & Interfaces

Transition

Test Move to Production

Deploy

Retrofit Customizations

End-user Training

System & User Test

Production Go-Live

© 2013 Board of Regents of the University System of Georgia. All Rights Reserved.

8

Upgrade Timeline Sep–Dec 2013

Current State Analysis

Jan-Apr 2014

Fit/Gap Mar-Jun 2014

Design

May-Sep 2014

Application Configuration Retrofits Oct 2014 – Feb 2015

System Testing Dec 2014 – Training Feb 2015

June 2014

September 2013

May - Oct 2014

© 2013 Board of Regents of the University System of Georgia. All Rights Reserved.

UAT

Feb 2015– Mar 2015

Go Live

April 2015

9

Fit/Gap Session Schedule MODULE

Start Date

Finish Date

Duration

Asset Management

Wed January 22

Thur January 23

2 days

Budget

Tuesday January 28

Thur January 30

3 days

General Ledger & KK

Tuesday February 4

Friday February 7

4 days

ePro/SciQuest

Monday February 10 afternoon

Tuesday February 11

1.5 days

Purchasing

Wednesday February 12

Friday February 14

3

Accounts Payable

Tuesday February 18

Friday February 21

4

Expenses

Tuesday February 25

Friday February 28

4

Reporting & Queries

Thursday March 6

Friday March 7

2

Security

Tuesday March 4

Wednesday March 5

2

• All Sessions will be held in Athens in the ITS training room • Sessions will generally be 8:30 am – 12:00 pm and 1:30 pm – 4:00 pm © 2013 Board of Regents of the University System of Georgia. All Rights Reserved.

10

Fit/Gap Participation • Fit Gap Sessions are NOT a training session • Each participant needs to be an active contributor to the discussions • Module team decisions could be made during the session • Need to have a general understanding of the module processes and requirements at your institution © 2013 Board of Regents of the University System of Georgia. All Rights Reserved.

11

Fit/Gap Process • Fit Gap Sessions will be led by an Oracle Consultant with facilitation support by ITS • Consultant will demo 9.2 and discuss module area processes with participants with the goal of generating requirements • The consultant will be trying to understand why our process is what it is

© 2013 Board of Regents of the University System of Georgia. All Rights Reserved.

12

Fit/Gap Process • The consultant will then map our process and requirements into the application • The Consultant will be asking us WHAT, WHY, HOW, and WHEN we do these processes or sub-processes • The final deliverable is a Requirements Document

© 2013 Board of Regents of the University System of Georgia. All Rights Reserved.

13

Fit/Gap Session Logistics • All sessions will be held at ITS in Athens: 2500 Daniels Bridge Road #300 (1st brick building) • ITS Training Room is located on first floor to the right • Hotel accommodations at Springhill Suites – Located within site of the ITS building – 3500 Daniels Bridge Rd Athens, GA, (706) 353-8484 – Ask for ITS BOR rate of $82

• Feel free to contact David Nisbet (706)583-2094 or [email protected] © 2013 Board of Regents of the University System of Georgia. All Rights Reserved.

14

Q&A

© 2013 Board of Regents of the University System of Georgia. All Rights Reserved.

15

Application Upgrade and Fit/Gap WebEx Q&A Q: Is there a limit to the number of attendees from each institution? A: Yes. Only one representative from each institution selected for a particular fit/gap session should attend. Not every institution will be represented at every fit/gap session.

Q: Will viewing from campus be available for the fit/gap session? A: Yes. We plan to broadcast the fit/gap sessions via WebEx or conference call. Participation will not be possible via WebEx (only onsite at ITS), but those who would like to observe the sessions may do so remotely.

Q: Can you publish a list of the participants designated to attend each fit/gap session? Yes. We are still waiting to receive confirmation from a couple of institutions about their representatives. As soon as that has been finalized, we will publish the list of the representatives that each institution has identified to participate on the GeorgiaFIRST website and will post an announcement to the listservs.

Q: Will a notice be sent to the registrants for each fit/gap session? A: No. Please see the session schedule and the logistics included in the slide presentation for details.