Pre-Construction Activities - Oregon.gov [PDF]

Pre-Construction Activities .... Please notify the Contract Administration Unit, In the Construction Section at the ODOT

0 downloads 5 Views 984KB Size

Recommend Stories


The Austin Company Preconstruction Services
Where there is ruin, there is hope for a treasure. Rumi

Possible Activities -(PDF
If your life's work can be accomplished in your lifetime, you're not thinking big enough. Wes Jacks

DSP 210 Zinc Silicate Preconstruction Primer
Where there is ruin, there is hope for a treasure. Rumi

CONFERENCES (Morning) ActivitieS ActivitieS
Forget safety. Live where you fear to live. Destroy your reputation. Be notorious. Rumi

Adventurous Activities Adventurous Activities
When you talk, you are only repeating what you already know. But if you listen, you may learn something

Activities
We can't help everyone, but everyone can help someone. Ronald Reagan

Research Activities of INES-CEA (pdf)
The butterfly counts not months but moments, and has time enough. Rabindranath Tagore

Download the July Activities Calendar (PDF)
Never wish them pain. That's not who you are. If they caused you pain, they must have pain inside. Wish

Summer 2017 Parks & Recreation Activities Guide (pdf)
Pretending to not be afraid is as good as actually not being afraid. David Letterman

courses & activities
Learn to light a candle in the darkest moments of someone’s life. Be the light that helps others see; i

Idea Transcript


Pre-Construction Activities

Section 2.1

Pre-Construction Activities Section 2

Review Plans

Preparations Begin in the Office

January, 2017

1

Pre-Construction Activities

Section 2.1

Bridge Plans

January, 2017

2

Pre-Construction Activities

January, 2017

Section 2.1

3

Pre-Construction Activities

January, 2017

Section 2.1

4

Pre-Construction Activities

Section 2.1

Early Plan Review • Review preliminary and advance plans and specifications to minimize discrepancies on final plans. • Check dimensions, angles, elevations, etc. • Look for inconsistencies • Inform PM & EOR about needed changes.

Plan Review Exercise • Review the following bridge plan, footing plan and girder schedule. • What items would you be concerned about when laying out the piling?

January, 2017

5

Pre-Construction Activities

January, 2017

Section 2.1

6

Pre-Construction Activities

Section 2.1

Review Contract Documents

Contract Documents Include: • Plans • Standard Specifications • Supplemental Specifications • Special Provisions • Change Orders

January, 2017

7

Pre-Construction Activities

Section 2.1

Order of Precedence Exercise • Standard Specifications

___

• Project Plans

___

• Standard Drawings

___

• Contract Change Orders

___

• Other Contract Documents Not Listed

___

• Special Provisions

___

• Supplemental Specifications

___

• Approved, Unstamped Working Drawings

___

• Reviewed, Stamped Working Drawings

___

Order of Precedence Exercise

January, 2017

• Standard Specifications

8

• Project Plans

3

• Standard Drawings

5

• Contract Change Orders

1

• Other Contract Documents Not Listed

9

• Special Provisions

2

• Supplemental Specifications

7

• Approved, Unstamped Working Drawings

6

• Reviewed, Stamped Working Drawings

4

8

Pre-Construction Activities

Section 2.1

Order of Precedence (00150.10(a)) 1. Contract Change Orders 2. Special Provisions 3. Project Plans 4. Reviewed, stamped Working Drawings 5. Standard Drawings 6. Approved Unstamped Working Drawings 7. Supplemental Specifications 8. Standard Specifications 9. Other Contract Documents Not Listed

Order of Precedence Cont’d: Notes on a drawing shall take precedence over drawing details. Dimensions shown on the drawings, or that can be computed, shall take precedence over Scaled dimensions.

January, 2017

9

Pre-Construction Activities

Section 2.1

Contract Document Review Includes: • Plan dimensions and angles • Horizontal and vertical control information • Elevations (deck, beam seat, footings, etc) • Soil logs, soil reports and other foundation information • Reinforcement details

Contract Document Review Includes: • Material quantities • Review and note any special features or unusual requirements • Field testing requirements • Review ODOT Nonfield-Tested Material Acceptance Guide

January, 2017

10

Pre-Construction Activities

Section 2.1

Field Testing (00540.16) Sample & Test Per MFTP

January, 2017

11

Pre-Construction Activities

Section 2.1

QC Testing Frequency

QC Testing Frequency Example

Bridge Deck Pour: 350 cy of HPC4350. How many sets of cylinders are required? 350 cy / (100 cy/set) = 3.5 = 4 sets

January, 2017

12

Pre-Construction Activities

Section 2.1

QC Testing Frequency Exercise

Bridge Deck Pour: 850 cy of HPC4350. How many sets of cylinders are required?

QC Testing Frequency Exercise Key Bridge Deck Pour: 850 cy of HPC4350. How many sets of cylinders are required? 600 cy / (100 cy/set) + 250 cy / (200 cy/set) = 6 + 1.25 = 6 + 2 = 8 sets

January, 2017

13

Pre-Construction Activities

Section 2.1

QA Testing Frequency

QA Testing Frequency Example

Total of 400 cy of HPC4350 for project. How many QA tests are required? 400 cy / (500 cy/test) = 0.8 = 1 QA test

January, 2017

14

Pre-Construction Activities

Section 2.1

QA Testing Frequency Exercise

Total of 750 cy of HPC4350 for project. How many QA tests are required?

QA Testing Frequency Exercise Key Total of 750 cy of HPC4350 for project. How many QA tests are required? 750 cy / (500 cy/test) = 1.5 = 2 QA tests

January, 2017

15

Pre-Construction Activities

Section 2.1

MFTP 4B

January, 2017

16

Pre-Construction Activities

January, 2017

Section 2.1

17

Pre-Construction Activities

Section 2.1

NFTMAG Exercise What acceptance documents are required for the following? • Rebar on QPL.

___________

• Rebar not on QPL.

___________

• Epoxy Rebar on QPL. ___________

NFTMAG Exercise Key What acceptance documents are required for the following? • Rebar on QPL.

O, F & QPL

• Rebar not on QPL.

T, O, L & F

• Epoxy Rebar on QPL. O, F & QPL

January, 2017

18

Pre-Construction Activities

Section 2.1

After Document Review • Report any discrepancies to your Project Manager. • Contact Engineer of Record for clarification.

Pre-construction Conference • Hold pre-construction conference prior to any work beginning. • Should be held within 30 days of the notice to proceed.

January, 2017

19

Pre-Construction Activities

Section 2.1

Contractor Submittals • Work schedules • Traffic control plans • Subcontractor approvals

Contractor Submittals Cont’d: • Material approvals Identification of concrete plants and prefabrication plant Concrete mix designs • Working drawings

January, 2017

20

Pre-Construction Activities

Section 2.1

Working Drawings Approved submittals required for the following: Shoring, cribbing, or cofferdams Falsework and load bearing forms Prefabricated items Post-tensioning Fabricated steel items, and Reinforcing steel

Plans Keeping up with the latest information . . . . BID PLANS WORKING PLANS (SHOP DRAWINGS & SUBMITTALS) AS-BUILT PLANS

January, 2017

21

Pre-Construction Activities

Section 2.1

Record Keeping See Appendix C For Forms

General Daily Progress Report

January, 2017

22

Pre-Construction Activities

Section 2.1

Daily Force Account Record

In the Field

January, 2017

23

Pre-Construction Activities

Section 2.1

On-Site Familiarization • Determine the locations of existing utilities. • Note any features or circumstances that may require special attention such as wetlands or endangered species habitat. • Ensure the proper implementation of the traffic control plan.

Staking

January, 2017

24

Pre-Construction Activities

Section 2.1

Staking Responsibilities • Determined by Contract – Agency provided construction stakes, lines and grades – Contractor provided construction stakes, lines and grades

Accompany Survey Crew • Find out where the stake locations are and what notations are used • Promotes discussion of plan location interpretations between Inspector, Surveyor, and Contractor • Check accuracy of staking by measurements and cross measurements

January, 2017

25

Pre-Construction Activities

Section 2.1

Preserving Stakes & Monuments The contractor is responsible for preserving stakes and monuments; accurately using these controls; and setting own stringlines, batterboards, etc.

Staking • Horizontal alignment –

Centerline stakes



Reference points

• Vertical alignment

January, 2017



Benchmarks



TBM’s



Grade stakes

26

Pre-Construction Activities

Section 2.1

Staking Tolerances (SP00305.40)

Staking Tolerances (SP00305.40) Substructures: +/- 0.03 ft (3/8”) for horizontal & vertical position.

Superstructures: +/- 0.02 ft (1/4”) for horizontal & vertical position.

January, 2017

27

Pre-Construction Activities

Section 2.1

Horizontal Alignment • Start with running in centerline – Set control points (Curve points, POT’s, etc.) – Set abutment and bent centerlines where possible

• Set reference points – For abutment and bents where possible

Distances • Lengths are divided into 100 foot long sections called stations. • Interval stakes along an established line are ordinarily laid down at 100 foot intervals called full stations. • If a marker stake is placed elsewhere along the line, it is called a plus station. Example: A point half way between station 10 & 11 is labeled “10+50”

January, 2017

28

Pre-Construction Activities

Section 2.1

Station Equation Example Const Line has equation 10+50Bk=10+80Ah Bent 1 has station of 10+00 Bent 2 has station of 11+30 What is the distance between bents? (11+30)-(10+00)-((10+80)-(10+50))= 130 ft – 30 ft = 100 ft

Station Equation Exercise Const Line has equation 12+10Bk=12+90Ah Bent 1 has station of 11+50 Bent 2 has station of 14+00 What is the distance between bents?

January, 2017

29

Pre-Construction Activities

Section 2.1

Station Equation Exercise Key Const Line has equation 12+10Bk=12+90Ah Bent 1 has station of 11+50 Bent 2 has station of 14+00 What is the distance between bents? (14+00)-(11+50)-((12+90)-(12+10))= 250 ft – 80 ft = 170 ft

Reference Points

January, 2017

30

Pre-Construction Activities

Section 2.1

Reference Points • Reference points or offset stakes are usually 2”x2”x14” wood stakes (hubs) driven flush with ground surface • A tack or small nail on the top of the wood stake marks the exact reference point • At least two permanent points should be set for each abutment

January, 2017

31

Pre-Construction Activities

January, 2017

Section 2.1

32

Pre-Construction Activities

January, 2017

Section 2.1

33

Pre-Construction Activities

Section 2.1

Common Staking Errors • Using incorrect working line • Staking and elevation controls have been disturbed – Always check control points against previous work

• Not checking bench marks prior to start of construction

Common Staking Errors Cont’d: • Not tying into a second bench mark when setting or checking elevations • TBM’s are set in a level circuit, not a side shot • Turning the wrong skew angle

January, 2017

34

Pre-Construction Activities

Section 2.1

Staking for Structures The layout of the structure and the references should be double checked by using a different survey approach. All survey notes should also be independently checked.

Benchmarks Place On New Bridges

January, 2017

35

Smile Life

When life gives you a hundred reasons to cry, show life that you have a thousand reasons to smile

Get in touch

© Copyright 2015 - 2024 PDFFOX.COM - All rights reserved.